| At ITT Aerospace, in Fort
Wayne, Indiana, we build many different kinds of specialty
payloads, including some of the workhorse instruments
on NASA and NOAA's meteorological satellites. These instruments
provide many of the pictures that you see on the evening
news and The Weather Channel. I like to think we're not
only in the aerospace business, but also in the business
of protecting lives and property. We take our responsibility
seriously, and that means sometimes we have to make tough
decisions.
We've got a very good on-orbit history with our instruments.
Like most folks in this business, however, we've had
occasional difficulties during production due to various
technical problems. Some years ago, we had a problem
like this on the Polar Orbiting Environmental Satellite
(POES) instrument program. In this case, our schedules
were slipping, threatening the prime spacecraft contractor's
schedule and putting us in a potential cost overrun
situation.
This program had been going on long enough that key
personnel from the teams at both NASA Goddard and at
our offices in Fort Wayne had changed many times. For
a while, we had an incompatible mix of personalities,
and there was a strained relationship between the project
teams. NASA's confidence in us was eroding, and that
was showing in the award fees, which were dropping.
The business implications here for a contractor are
severe, because award fees can be the only profit on
certain types of contracts.
At the time, I was ITT's Director of NASA Programs
and I knew that I needed to take action to improve the
situation. I decided to make certain personnel changes
in our program management office to provide a more compatible
mix. I also assigned additional systems engineering
expertise to our team. In short order, the relationship
and performance started improving. Things were getting
better. Then, the backslide began when a $10M instrument
was damaged by electrical overstress during final acceptance
testing.
Following the root cause investigation, we thought
we understood the problem, and implemented appropriate
corrective action. But when we resumed testing, another
instrument showed damage. Now we were both confused
and in trouble. We had two instruments that were damaged
for reasons not understood, and we were uncertain where
the overstress had occurred in the testing. Once again,
our schedule was threatened.
| The decision
could mean heaven or it could mean hell. |
The team faced internal pressures to hold schedule because
ITT was involved in a competition for a new project. Past
performance to schedule was a critical element of the
competition. Should we try to "limp along" with instrument
testing to make at least some level of schedule progress
in parallel with troubleshooting the problem -- or should
we take the more radical approach and shut down all testing
while we investigated? What would ITT senior management
think if we shut ourselves down when they knew we were
already in schedule trouble? What would NASA management
think if we shut ourselves down? As the Eagles put it
in their song "Hotel California," the decision "could
mean heaven or it could mean hell." What do you do?
The skies begin to clear
A decision of this magnitude would affect the entire
team so everyone's voice was important in making this
decision. I assembled the project team, including technicians,
engineers, scientists, and business management -- and
we discussed the situation. We all agreed that we needed
to do the right thing, no matter what. The decision,
as you would suspect, was unanimous. We would shut ourselves
down while we investigated. We could not put additional
flight hardware at risk. While all agreed it was the
right thing to do, both NASA and ITT management hoped
that the problems would be found and resolved quickly.
 |
| Inspection of
the POES, NOAA-M, Advanced Very High-Resolution
Radiometer (AVHRR) instrument scan mirror. (Click
image for a closer look.) |
We worked many long days trying to understand the causes
of the problem using a cooperative team of both ITT and
NASA experts. What we found was not just one, but up to
three potential causes of electrical overstress. Taking
corrective action for one did not correct the others.
All of these issues were caused by recent changes made
in the test process. Misleading symptoms compounded the
problems. The initial electrical overstress that we were
subjecting the instruments to resulted in greater stresses
and damage once the instrument was powered on. The power
supplies of the instrument itself were causing damage
due to the first overstress, which was weakening the part.
The investigation showed that we had recently "improved"
our test labs to reduce the susceptibility to voltage
transients. In keeping with the adage that "one of the
biggest causes of problems is solutions," we found that
there were potential grounding issues with the new wiring.
In addition, we found that a long interconnect cable
on a new piece of test equipment could generate 200
volts of static charge when moved if we did not have
an adequate bleed-off path. We also found that this
cabling was susceptible to cross-coupling any damaging
static charge on one wire to other wires in the cable,
potentially causing further stress. All of these issues
were factors in our damaged instruments.
After the first instrument was damaged, we stopped
the investigation when we found conclusive evidence
of a cause and corrected it. What we did not do was
dig deeper to investigate the possibilities of multiple
causes and eliminate them all. Following this last round
of exhaustive troubleshooting and repair activities,
which took over two months, the ITT team presented its
findings to a NASA review board explaining the issues,
the findings, and the corrective actions taken. Our
final statement was, "We now feel that it's safe to
resume testing."
The board agreed with us, and testing was successfully
resumed and has been fine ever since. We resumed instrument
deliveries and we were able to recover the lost schedule
in about ten months. Fortunately, we escaped impacting
the spacecraft-level test schedule.
A forecast for success
Because all of us, the government and the contractor,
were working together, we were able to take a synergistic
approach to problem solving, even in a pressured environment,
and to agree on what we were doing and why. Perhaps
one of the biggest lessons for the team was that even
some of the bleakest-looking situations can be overcome
when you combine the right level of leadership, teamwork,
and persistence with a few tools from your toolbox.
It was not a comfortable decision to make, but it was
the right decision to shut ourselves down.
After this episode, our award fee started moving in
the right direction, and has returned to the excellent
range. The ITT and NASA/NOAA program teams continue
to work diligently together in producing some of the
best meteorological products in U.S. history.
Lessons
- Leadership requires courage to make the right decision,
even if it is a painful decision.
- Involve the entire team when making critical decisions.
"Involvement" means open and honest communications
that include internal and external customers.
Question
Would you have shut down the project after the first instrument
was damaged, the second one, or only after a third?
Search by lesson to find more on:
As
a NASA contractor, Larry Goshorn successfully
managed a variety of payload projects, including
the GOES and POES meteorological satellite sensor
programs. In 2003, he retired as the Director of
Space Programs at ITT Aerospace/Communications in
Ft. Wayne, Indiana -- after receiving the company's
highest recognitions, the Harold S. Geneen Award
and the Gold Ring of Quality. He was an aerospace
program manager for 28 years.
Goshorn's story, "A Stormy Situation," was originally
presented at the 7th
APPL Masters Forum of Project Managers,
held in Annapolis, Maryland in August 2003. Many
of the stories in ASK Magazine originate
as Masters Forum presentations. The Masters
Forum is held twice a year, bringing together
some of NASA and the industry's top project managers
for three days of knowledge sharing.
We featured a brief story by Goshorn at the
end of Marty Davis' story "A
Good Man Is Hard to Find" in Issue 15
of ASK, about a teambuilding exercise involving
an elephant, three managers, and a front-page
story in the New York Times about a troubled
NASA program. It was originally told impromptu
at another Masters Forum and has probably been
retold by the people who were there more times
than they can count. |
|